Capital Program Scope of Work - Smith Clove Elementary School

Replacements and Upgrades

Boiler and heating system replaced = $2,379,000

Smith Clove's boilers were installed in 1968. At 54 years old, they are tied with the Middle School as second oldest in the district.

Upgrade safety systems = $724,680

Upgrade fire alarm and carbon monoxide monitoring systems

Improve security system = $292,800

A security vestibule will be created to provide Raptor system ID verification at the front entry, rather than at the rear of the lobby.

This new security vestibule might be similar to the one at the high school

Summary

Smith Clove Elementary School

Total cost at Smith Clove = $3,396,480

Project

Cost

Replace boilers

$2,379,000

Upgrade fire alarm and carbon monoxide monitoring systems

$724,680

Add a security vestibule to the front entry

$292,800

Total

$3,396,480