Capital Program Scope of Work - Smith Clove Elementary School
Replacements and Upgrades
Boiler and heating system replaced = $2,379,000
Smith Clove's boilers were installed in 1968. At 54 years old, they are tied with the Middle School as second oldest in the district.




Upgrade safety systems = $724,680
Upgrade fire alarm and carbon monoxide monitoring systems
Improve security system = $292,800
A security vestibule will be created to provide Raptor system ID verification at the front entry, rather than at the rear of the lobby.
This new security vestibule might be similar to the one at the high school


Summary
Smith Clove Elementary School
Total cost at Smith Clove = $3,396,480
Project | Cost |
---|---|
Replace boilers | $2,379,000 |
Upgrade fire alarm and carbon monoxide monitoring systems | $724,680 |
Add a security vestibule to the front entry | $292,800 |
Total | $3,396,480 |